Nov. 18, 2009 — Architect Robert Summerfieldt recently told Grayson City Council progress on construction of the new fire department is going well with a completion date of spring expected.
Summerfieldt visited November’s regular meeting with the field report and request for payment in the amount of $31,076.91 with a balance of $739,327.76 to be owed as the work continues.
“Everything is going excellent,” he told council. “We do expect to have the roof on this week.”
Work presently in progress includes installing structural steel and steel trim items, installing the roof insulation system, installing metal studs and plumbing layout and preparations.
Work still anticipated on the building includes structural steel, siding, roofing and plumbing.
Summerfeldt said among the issues discussed included ironwork nearly completed and additional adjustments still required around the tower.
Other issues on the field report included:
• Plumbing work commencing and resolving some confusion concerning where the drinking fountain would be located
• Plumber has proposed changing the gas piping specified to a different types. No change in cost required but more rapid installation and simpler connections.
• Detail conditions at masonry work at the tower base discussed and resolved
• Changes resulting from meeting on keying and security systems still under consideration
Summerfeldt asked the council to accept a second and third change order, putting the change totals to $13,872.
Change order #2 included:
• Increase in water tap fee from $9,500 in the construction contract and adding $1,950
• Add vinyl tile to the kitchen floor prior to kitchen equipment installation and add $339.96 to cover the deletion of floor covering made prior to construction bidding in order to cut costs.
• Keypad door locks to be provided by owner and installed by contractor during general construction, G.C. to deduct original locks from contract and provide labor to install owner’s locks in exchange for adding window lights to doors as reviewed with the fire department personnel.
• Deduct $300 for the cost of the project construction sign
Change order #3:
• Change to HVAC breakers and starters – pending
• Change specific black steel gas piping to corrugated stainless steel piping system with corresponding changes in regulators, system pressure, all in accordance with code and utility company requirements – no change pending approval by engineers.
The net amount of $1,989.96 resulted in change order #2, Summerfieldt reported to council. No costs were added per change order #3. Mayor George Steele told Summerfieldt he and the council were pleased project appeared to on target for a spring completion. “You guys are doing a great job over there,” Steele added. “ I know all of us are anticipating this getting done.”
- Local News
-
-
Grayson Tourism office officially opens
The Grayson Tourism Commission officially opened the log cabin at the Grayson City Park Monday.
-
The Writing's on the Wall
The rain came in such abundance that it flooded most of downtown Olive Hill on May 2 of this year.
-
Grayson City Council meets
The Grayson City Council met in regular session this past week with a long agenda including the first reading of the 2010 – 2011 budget and setting the date for trick-or-treat.
-
Flood victims to get new furniture
Thanks to the Church of Christ National Relief Fund, many May 2 flood victims will get the chance to start over with new furniture.
-
Olive Hill struggles with dirty water issue
For the past few weeks, drinking water, clean clothes and taking showers had been a problem for much of Olive Hill’s residents. In fact, concerns over dirty tap water sent many folks to Grayson to do laundry and to grocery stores for bottled water.
-
County to make payments on new cruisers and fire department equipment
The Carter County Fiscal Court made a motion Tuesday to amend the 2010 –11 budget to begin payments on four new police cruisers and fire department equipment.
-
Two Grayson KSP promoted
Two Grayson residents have been promoted by the Kentucky State Police.
-
Tom T. Hall honored in the Country Music Quilt Trail
From the hills of Appalachia in Olive Hill, the songs of “The Storyteller”, Tom T. Hall, burst through the air like the sun as it faithfully rises over the knobs in Carter County.
-
Two indicted
A Carter County Grand Jury indicted two individuals on Aug. 20.
-
Ms. Gee and Mrs. Horsley go to Washington
It was a rare occasion when two educators from Carter County received a special invitation to attend a reception and luncheon at the National Press Club in Washington, D.C.
- More Local News Headlines
-